I have so much drawing work to do at the moment that I can't get a good run at the house, but over the last couple of weekends I have made a start on the bathroom.
To re-cap, the bathroom is going in the middle of the upstairs of the old part of the house, wrapped around the stairwell. The first job was to get all the plumbing into the floor, and leave "tails" up to connect to the various bits of sanitaryware in due course. I can't say plumbing is my favourite thing on the planet.
Anyway, here is the completed plumbing. In the following photo, the hot and cold feed come through (well, under) the white wall at the top left of the picture. They're in 22mm copper, and we'd just poked them through into the floor void when we were doing all the work in the new part of the house. As it happened, they weren't in the most convenient location. The general principle here is to use 22mm for as long as possible, and with long swept bends, so that flow rates particularly for the bath, remain high. This picture show hot and cold running along the wall, and two feeds for the shower tee-ing off in 15mm (they're going into a wall, so there is no choice in the matter). The two tails sticking up nearest the camera are for the hand basin:

Stairwell is on your left in this photo, and it shows the tails for the basin (nearest us), and then on to the bath supply on the far left of the view:

After the bath (nearest), the supply heads off to serve the downstairs toilet, and the cold (capped) will run around to the loo in time (too much stuff in the way at the moment):

I mainly used traditional end-feed fittings, with a few old Yorkshires I had left over here and there:

When I had checked everything, drained the system down, and made the final connections, it was time to refill and test. I didn't need to run a dusty finger under each joint to find leaks, in the normal way. No, it was spraying against the wall like a pressure wash! That meant racing to turn the water off again, drain everything down, mop up the puddle which had run through the floor and ceiling into a puddle downstairs, get everything dry, heat the joint up a bit, apply copious amounts of flux, and then heat it properly and add some more solder.........all the while hoping that there wasn't remnant water at the joint which would render the joint useless. Anyway, it worked, and nothing else leaked. Phew..........that's a nasty job behind me. Insulating was a 5 minute job (you need zip ties), and you can see the pipe benders in the foreground):

Time for the floor:

I used new hand-made nails:

The old floor is all over the place. The joists are all over the place. My new boards were much thicker than the existing boards. So all in all, much messing around trying to get a semi-reasonable floor:

This is all I needed to put down to enable me to start on the walls. I'll fill in the missing boards later. I then built the wall between the landing and the bathroom, using 3" (70x45 PSE) timber:



The above photo shows the raised bit above the stairwell. There will be a short sloped ceiling over part of the stair, which will have a shelf and cupboard over it in the bathroom (and forms a useful pipe-run for the basin waste).

Finally, I'm going to have fun sorting this ceiling out:

To re-cap, the bathroom is going in the middle of the upstairs of the old part of the house, wrapped around the stairwell. The first job was to get all the plumbing into the floor, and leave "tails" up to connect to the various bits of sanitaryware in due course. I can't say plumbing is my favourite thing on the planet.
Anyway, here is the completed plumbing. In the following photo, the hot and cold feed come through (well, under) the white wall at the top left of the picture. They're in 22mm copper, and we'd just poked them through into the floor void when we were doing all the work in the new part of the house. As it happened, they weren't in the most convenient location. The general principle here is to use 22mm for as long as possible, and with long swept bends, so that flow rates particularly for the bath, remain high. This picture show hot and cold running along the wall, and two feeds for the shower tee-ing off in 15mm (they're going into a wall, so there is no choice in the matter). The two tails sticking up nearest the camera are for the hand basin:

Stairwell is on your left in this photo, and it shows the tails for the basin (nearest us), and then on to the bath supply on the far left of the view:

After the bath (nearest), the supply heads off to serve the downstairs toilet, and the cold (capped) will run around to the loo in time (too much stuff in the way at the moment):

I mainly used traditional end-feed fittings, with a few old Yorkshires I had left over here and there:

When I had checked everything, drained the system down, and made the final connections, it was time to refill and test. I didn't need to run a dusty finger under each joint to find leaks, in the normal way. No, it was spraying against the wall like a pressure wash! That meant racing to turn the water off again, drain everything down, mop up the puddle which had run through the floor and ceiling into a puddle downstairs, get everything dry, heat the joint up a bit, apply copious amounts of flux, and then heat it properly and add some more solder.........all the while hoping that there wasn't remnant water at the joint which would render the joint useless. Anyway, it worked, and nothing else leaked. Phew..........that's a nasty job behind me. Insulating was a 5 minute job (you need zip ties), and you can see the pipe benders in the foreground):

Time for the floor:

I used new hand-made nails:

The old floor is all over the place. The joists are all over the place. My new boards were much thicker than the existing boards. So all in all, much messing around trying to get a semi-reasonable floor:

This is all I needed to put down to enable me to start on the walls. I'll fill in the missing boards later. I then built the wall between the landing and the bathroom, using 3" (70x45 PSE) timber:



The above photo shows the raised bit above the stairwell. There will be a short sloped ceiling over part of the stair, which will have a shelf and cupboard over it in the bathroom (and forms a useful pipe-run for the basin waste).

Finally, I'm going to have fun sorting this ceiling out: