It isn't a dumb question at all, Bob. In fact, it is a very important one.
The concrete stays dry because of the DPM underneath, and because the upper edge of the slab is above ground level, enabling it to dry with air movement. I will be cutting the polythene back to where it turns up the edge of the slab. If I were to leave the polythene up the edge of the slab and tuck it under the brickwork, UV would destroy it in no time flat. Obviously things would be very different if the slab were below ground level, but some of mine (at the back) is about 9 inches above ground level.
We're talking about 160 to 350mm of C35 concrete here, and whilst I wouldn't advocate it, it would probably stay dry if there were no DPM at all. There is no way of having the DPM stop at ground level, even if you wanted it to. The DPC will be on top of the plinth, under the timber, and this is mainly because bricks absorb moisture then release it slowly, thus can remain damp for some while.
The proof of this particular pudding is in the eating, and the way to test for moisture in a slab is to put a piece of plastic on top of it for a day of two, and see if a dark patch emerges. Well, I did this with my previous workshop built to this same design, and it was dry as a bone.