Hello mate
Haha not quite yet. been a busy few weeks for me with work and personally and he's been finishing off a job at a mate of mine so been on and off it here. There's some progress but not massive and I've been too busy to sit down and write an update.
Here's where we are currently…
A couple of days after the last update I ordered the remainder of the materials to do the slab and Darek came round and met the delivery. 6 tons of MOT hung over the hedge and he cut the bags to drop it roughly into position then spread it, tamped, whackered then did the same with the sand…
I then went out for a bit with the kids and got back to find him having laid and taped the DPM, then laid and taped the 100mm Kingspan under the slab, then laid and taped a second DPM then laid the steel mesh. He left one end open for me to inspect when I got back but my phone died and was charging so sadly no photo's.
That was all done on the Thursday and I arranged for a concrete delivery for 9am Saturday morning which Darek came to meet while we went down to London for my nephew's birthday for the weekend. Got back covered in bruises after a whole Saturday playing paintball, to find this…
Which the wife enquired as to whether it was okay to walk on, the kids didn't bother checking…
And here it was on last Monday morning. Is actually a lot smoother than it looks so very pleased.
He's given me a list of materials for the next phase which I am ordering today and hopefully he will then be on this from later this week until finished, assume the weather lightens up a little so it's not too cold to lay bricks…
Mike has very kindly validated some questions on my steelwork for me and I've to go back to the structural engineer on a couple of things, then hopefully full steam ahead from later this week, or next week at the latest.
Cheers
Mark