OK, so this weekend was D Day for the floor in the workshop.
So, first job was a bit of tidying up and some sweeping.
You'll no doubt have spotted my slippers in the foreground. Not a style statement, but it was wet and I wanted to avoid getting the floor of the workshop wet by going back and forth and then trapping this moisture in the floor.
I decided to just move most of the clutter to one end and start laying the other end, rather than clear the whole lot out. Then I cut a sheet of damp proof membrane to cover the floor.
When I bought the floor insulation I have to cut it in half to get it into the car - I got some funny looks in B&Q on my hands and knees just beyond the till cutting the 8' x 4' sheets in half :lol: . It didn't cut that cleanly as I was trying to get it done quickly, but that did at least mean it was easy to work out which piece went with which when I cam to put it down.
I then started to cut the flooring boards themselves. I clamped the first two together as I wanted to trim the tongues off so I a had a solid edge at the start.
Having read some of Steve M's thread on UKW I had the benefit of all the retrospective tips he had been given. So tongues forward, which did indeed make things very easy when it cam to applying glue. Progress was pretty smooth. I used a block and a hammer to close the 'front to back' joints. When I got to the far side of each run of boards I used leverage to close all the 'side to side' joints.
By the end of day 1 I had managed just under half, not great but the morning and lunchtime was spent buying the insulation and a family visit to Costco (I know how to treat my kids).
At the start of this morning I used a (very) old chisel to scrap away the squeezed out glue, whilst the joints were already very tight the squeeze out completely sealed them, so no worries about trying to grout them I'm very pleased to say. I then moved all the clutter to the far end of the workshop so I could carry on laying the floor.
Then just cut, glue, lay repeat...
At the end I had to cut the last piece of insulation into three thin strips to fit, glad to say that with more time and being careful allowed me to get a much better edge on the insulation.
Now, the width of the workshop was almost perfect for one and a half lengths of flooring board, almost. As I worked along each row I had to steal a little more from the last board and by the end this was the cumulative result of this process.
Maybe it would have been possible to avoid this, but with the way I cut the boards this little section had to be filled with a small section T&G'ed to the preceding row, but butt jointed to the penultimate piece. I ensured plenty of glue on this joint and with the small piece tight in the corner and fully supported by the insulation I thin it should be OK once it has had time for the glue to dry fully.
Well I'm happy with the results of the last couple of days, just wondering now if I can manage to sneak enough time tomorrow morning to put a first coat of paint on the floor before we head to my sister and brother in law for a family Easter Sunday lunch. :eusa-think:
Terry.